Albanese government abandons beleaguered inland rail project connecting NSW with Queensland

The Guardian Krishani Dhanji 1 переглядів 4 хв читання
Australian Infrastructure Minister Catherine King speaks during question time
The infrastructure minister, Catherine King, said federal Labor was ‘taking sensible decisions to realign the future of Inland Rail’, with $1.75bn of the project’s funding reallocated to other national rail upgrades. Photograph: Lukas Coch/AP
The infrastructure minister, Catherine King, said federal Labor was ‘taking sensible decisions to realign the future of Inland Rail’, with $1.75bn of the project’s funding reallocated to other national rail upgrades. Photograph: Lukas Coch/AP
Albanese government abandons beleaguered inland rail project connecting NSW with Queensland

Originally envisioned to run 1,700km from Melbourne to a port near Brisbane, the mega infrastructure project will now only connect Beveridge in Victoria to Parkes in NSW

The Albanese government will drastically scale back the beleaguered inland rail project, abandoning plans to connect country NSW and Queensland by rail, as the price tag blows out to more than $45bn.

Originally envisioned to run 1,700km from Melbourne to a port near Brisbane, the mega infrastructure project will now only connect Beveridge, on the outskirts of Melbourne, to Parkes in central-west New South Wales – about half the distance – with the government reallocating $1.75bn of the funding to other national rail upgrades.

The cost has increased more than 50% in just three years, since Dr Kerry Schott was commissioned by Labor in 2023 to independently review the project.

Schott estimated the project would be completed by 2031 and cost upwards of $31.4bn – a doubling of the previous estimate – which she called “astonishing”, adding she was not confident on the figures.

Sign up for the Breaking News Australia email

Further independent costings, commissioned by Inland Rail, found the project would now take until 2036.

The decision will effectively see the end of the Inland Rail vision, though the government is still seeking environmental and state approvals and preserving areas of land where the project is intended to be built, through northern NSW and south-eastern Queensland.

Delivering the freight link to Parkes will allow double-stacked freight trains to run west to Perth and east to Newcastle from Beveridge. The government now expects construction between Parkes and Beveridge to be completed in late 2027.

The Coalition announced the project in 2017, with an estimated cost of $9.3bn. In 2020, the project’s estimated cost increased to $16.4bn, with a completion date of 2026-27.

Schott’s 2023 review had pointed to “immature preliminary designs and approval requirements”, prolonged approval processes and “recent escalations” as reason for the blow outs.

Map showing the originally planned Inland Rail route from Beveridge in Victoria to just south of Brisbane, with new shortened route to Parkes in central NSW

The government had budgeted just $14.5bn towards the freight link, and by abandoning half of the track while reallocating a portion of the funding will deliver a small improvement to the budget bottom line.

In 2024, then Inland Rail chief executive, Nick Miller, insisted the project was not “stalled” and that the government was still committed to the northern half.

The transport minister, Catherine King, has said repeatedly the government was “concentrating” on delivering the link between Melbourne and Parkes, but had remained committed to building the entire 1,700km line.

In February, after the government released a business case for high speed rail along the east coast, King told the ABC: “What we’ve learned from both high speed rail overseas and from rail cases here in Australia, such as Inland Rail, a failed Coalition project … is that you’ve got to get all of that design work done.”

High-speed rail is an Australian political punchline. After 50 years, will Labor’s newest proposal finally leave the station?Read more

On Tuesday, King said the $1.75bn of reallocated funding was critical, and followed “decades of underinvestment in the network”.

“The 2023 independent review found major deficiencies in the governance and delivery of Inland Rail by the Liberals and Nationals,” she said.

“We are taking sensible decisions to realign the future of Inland Rail and build a safe, efficient and reliable network for the future.”

Labor has also announced a new chair and chief executive of Inland Rail, after Schott criticised the board and subcommittee of Inland Rail, accusing them of not having “adequate skills to oversee this project”.

Dr Collette Burke has been appointed chair of the board, with Dr Sean Sweeney to take over as chief executive.

King said the $1.75bn will go to upgrades to the east coast network and the east-west corridor to improve high risk flood-prone sections.

An additional $55m will be spent to incentivise companies to shift from using road freight to rail or cargo ships.